Access Roads and structure pads prepare for Transmission line in Saudi Arabia, And proper work procedure and methods statement bellow, requirements Sub Grade, Sub Base layer and final layer. The Access road is connected to every Structure Pads and Towers. This roads is carriable heavy loads vehicle.
The Access road is not made of Cement concrete or metal pitch Roads. The access road and Pads are made of soil with stone and soil particles and compacted with water.

OBJECTIVE :
The objective of this Method Statements is a provide guideline, as per SEC (Saudi Electricity Company) Standes, for the CONSTRUCTION of ACCESS ROAD & STRUCTURE PADS.
SCOPE:
This method statement established the specific parameters and procedures for the construction of unpaved access road, structure pad and slop protection from erosion/ encroachment of transmission line for use of Overhead Transmission Line system of National Grid Saudi Arabia (NGCA) under the scope of Project Technical Specification (PTS) and SEC Standards.